纳米布矿业公司完成霍尔矿选矿厂扩建项目
Namib Minerals 已完成 How 矿山扩建选矿厂的调试工作,将处理能力提高了 36%,达到每月 55,000 吨,提前于计划完成。
为什么重要. Namib Minerals的加工能力提升将增强其黄金生产能力,影响其财务表现和运营效率。
Namib Minerals 已完成 How 矿山扩建选矿厂的调试工作,将处理能力提高了 36%,达到每月 55,000 吨,提前于计划完成。
为什么重要. Namib Minerals的加工能力提升将增强其黄金生产能力,影响其财务表现和运营效率。
Our focus now turns to a disciplined ramp-up to full capacity and to delivering the expected annualized run-rate of more than 30,000 ounces at current grades that we outlined on our recent call,
The Company’s focus now turns to ramping up processing capacity to 55,000 tonnes per month, with full capacity targeted to be achieved in December 2026.
Currently Namib Minerals operates the How Mine, an underground gold mine in Zimbabwe
Completion of the plant installation and commissioning is expected to increase How Mine's monthly processing capacity from approximately 40,500 tonnes to 55,000 tonnes.
Namib Minerals (NASDAQ: NAMM) is a gold producer, developer and explorer with operations focused in Zimbabwe.
In parallel, the restart of Redwing Mine remains on schedule, with first gold targeted by January 2027.
The commissioning represents a significant milestone for the Company, with an expected increase in milling capacity of approximately 36%.
New York, Oct. 08, 2026 (GLOBE NEWSWIRE) -- Namib Minerals ("Namib" or "the Company") (Nasdaq: NAMM), today announced the completion of commissioning of its expanded milling plant at How Mine. The Company notes the commissioning is ahead of the mid-October deadline previously…
Completion of the plant installation and commissioning is expected to increase How Mine's monthly processing capacity from approximately 40,500 tonnes to 55,000 tonnes. The commissioning represents a significant milestone for the Company, with an expected increase in milling cap…