ナミブ・ミネラルズがハウ鉱山におけるミリングプラントの拡張を完了

Namib Mineralsは、How Mineにおける拡張されたミリングプラントのコンミッションングを完了し、処理能力を36%増加させ、月間55,000トンに達しました。これはスケジュールより早く行われました。

なぜ重要か. Namib Mineralsの処理能力の増加は、その金鉱生産能力を向上させ、財務業績および運用効率に影響を与えることになる。

01

誰に影響するか

  1. 1Namib Minerals
  2. で事業展開 →事実
    2Zimbabwe地域
02

根拠

  • GGlobeNewswire public company news企業開示2026-10-09 05:15
    Our focus now turns to a disciplined ramp-up to full capacity and to delivering the expected annualized run-rate of more than 30,000 ounces at current grades that we outlined on our recent call,
    出典を見る
  • GGlobeNewswire public company news企業開示2026-10-09 05:15
    The Company’s focus now turns to ramping up processing capacity to 55,000 tonnes per month, with full capacity targeted to be achieved in December 2026.
    出典を見る
  • GGlobeNewswire public company news企業開示2026-10-09 05:15
    Currently Namib Minerals operates the How Mine, an underground gold mine in Zimbabwe
    出典を見る
  • GGlobeNewswire public company news企業開示2026-10-09 05:15
    Completion of the plant installation and commissioning is expected to increase How Mine's monthly processing capacity from approximately 40,500 tonnes to 55,000 tonnes.
    出典を見る
  • GGlobeNewswire public company news企業開示2026-10-09 05:15
    Namib Minerals (NASDAQ: NAMM) is a gold producer, developer and explorer with operations focused in Zimbabwe.
    出典を見る
  • GGlobeNewswire public company news企業開示2026-10-09 05:15
    In parallel, the restart of Redwing Mine remains on schedule, with first gold targeted by January 2027.
    出典を見る
  • GGlobeNewswire public company news企業開示2026-10-09 05:15
    The commissioning represents a significant milestone for the Company, with an expected increase in milling capacity of approximately 36%.
    出典を見る
  • GGlobeNewswire public company news企業開示2026-10-09 05:15
    New York, Oct. 08, 2026 (GLOBE NEWSWIRE) -- Namib Minerals ("Namib" or "the Company") (Nasdaq: NAMM), today announced the completion of commissioning of its expanded milling plant at How Mine. The Company notes the commissioning is ahead of the mid-October deadline previously…
    出典を見る
  • GGlobeNewswire public company news企業開示2026-10-09 05:15
    Completion of the plant installation and commissioning is expected to increase How Mine's monthly processing capacity from approximately 40,500 tonnes to 55,000 tonnes. The commissioning represents a significant milestone for the Company, with an expected increase in milling cap…
    出典を見る