Revolution Wind enters commercial operation with 65 turbines
The project reached commercial operations in October 2026, after its final turbine was installed the previous month. Its construction cost is reported as about $6 billion by one source and $6.2 billion by another.
The project has 65 offshore turbines, all identified as Siemens Gamesa SG 11.0‑200 DD models.12
Installation of the final turbine was reported in the month before the project entered commercial operation.1
Story
A completed project after a contested construction periodRevolution Wind reached commercial operations in October 2026, marking the project’s move into service after construction of its offshore installation. (The sentence’s timing and project status come from gCaptain.)1 The project comprises 65 offshore turbines, and all 65 are identified as Siemens Gamesa SG 11.0‑200 DD models. (Those descriptions establish both the project’s turbine count and the model used throughout.)12 The scale is therefore described by the same count in the project overview and the equipment specification, rather than by two different turbine totals. (Both sources give 65.)12 Construction cost is reported as about $6 billion in POWER Magazine, while Canary Media gives a figure of $6.2 billion. (The reports do not provide a reconciliation of the difference.)23 These figures are close but not identical, so the cost is best presented as a reported estimate rather than as one agreed exact amount. (The two cited accounts use different figures.)23
The final turbine was installed in September 2026, before commercial operations began the following month. (The two reported milestones place completion of turbine installation ahead of the start of operations.)1 That sequence distinguishes the last installation milestone from the operational milestone: the final turbine arrived first, and the project entered commercial service afterward. (The dates are reported by gCaptain.)1 The installation total of 65 turbines describes the project as a whole, while the September event concerns only the final turbine in that total. (The source reports the overall count and the last installation separately.)1 POWER Magazine identifies the complete set of turbines as Siemens Gamesa SG 11.0‑200 DD models, so the model description applies to all 65. (The report explicitly pairs the model with the full turbine count.)2 The available reporting gives these installation and operating milestones, but does not state a more detailed schedule for the construction period. (The cited facts identify the final installation month and the commercial-operation month.)1
Utilities in Rhode Island and Connecticut have power purchase agreements for the project, including Eversource and United Illuminating. (These arrangements identify utility counterparties in both states.)2 The agreements show which utilities are named in the project’s power-sale arrangements; the reporting does not give a customer count or household-level allocation. (The cited account lists utilities, not individual electricity users.)2 The project’s 65 turbines are a count of offshore equipment, not a measure of how many people or businesses receive electricity. (The sources separately describe turbines and utility agreements.)12 POWER Magazine names Eversource and United Illuminating among the utilities involved, while also placing the agreements in Rhode Island and Connecticut. (The account provides both company names and state locations.)2 The supplied information does not quantify the electricity allocated under those agreements, so their presence establishes purchasers without supplying a volume. (No contracted amount is reported in the cited fact.)2
The project faced a federal stop-work order in August 2025, when the Trump administration cited national security concerns. (That order preceded the reported commercial start.)1 A further suspension followed in December 2025 as part of a wider attempt to halt five offshore wind projects. (The report gives both the month and the number of projects in that effort.)1 A federal judge then granted a preliminary injunction that allowed work to continue. (The reported court action followed the suspension orders.)1 In sequence, the reporting describes two orders interrupting work and a judicial ruling permitting it to proceed. (The orders were issued in August and December 2025, and the injunction followed.)1 A supported account characterizes this episode as a conflict between the administration’s stated security concerns and judicial backing for offshore wind development. (That characterization is marked supported.)2
The project’s commercial start came after the stop-work and suspension orders and the preliminary injunction allowing work to resume. (The reported sequence links these events before the October 2026 operating milestone.)1 The account does not specify the duration of either interruption, so the dates alone do not establish how much construction time was lost. (The cited facts give order months but no delay calculation.)1 Nor does the reporting quantify the financial effect of the orders or the injunction on Revolution Wind’s construction cost. (The cost figures are reported separately from the legal events.)123 The supported description says the project is fully operational despite legal and political challenges and says it will provide clean electricity to New England’s grid. (This is presented as a supported account.)1 That account describes the project’s regional role, while the utility agreements specifically name counterparties in Rhode Island and Connecticut. (The two reports identify different aspects of the project’s reach.)12
Ørsted reported that EBITDA for the first nine months of 2026, excluding new partnerships, rose 19% to DKK 20.2 billion. (The measure and exclusion are part of the company figure reported by gCaptain.)1 That period-wide EBITDA figure appears alongside a third-quarter net loss of DKK 728 million, which covers a different reporting measure and time interval. (The source reports both figures.)1 The reported rise in EBITDA therefore should not be read as eliminating the quarterly net loss; the two indicators describe distinct results. (The facts report an increase in one and a loss in the other.)1 The nine-month EBITDA comparison excludes new partnerships, a qualification that limits what the stated increase represents. (The reported measure explicitly uses that exclusion.)1 The available figures do not provide a direct calculation connecting the project’s construction cost with either Ørsted financial measure. (The sources state these amounts separately.)123
Chief executive Rasmus Errboe said Ørsted was continuing to meet its strategic priorities and maintain strong financial performance. (gCaptain reported his assessment.)1 His statement is the company leader’s view, while the reported EBITDA increase and quarterly loss provide separate financial figures. (The source gives both the assessment and the measures.)1 The distinction matters because the EBITDA figure covers the first nine months and excludes new partnerships, whereas the net loss is identified for the third quarter. (The reporting specifies each measure’s scope.)1 The source does not attribute either financial result specifically to Revolution Wind, so they describe Ørsted rather than a project-level profit or loss. (The figures are reported for the company.)1 No project-specific revenue, operating margin, or contribution to those company results is given in the supplied reporting. (The cited financial facts contain no such breakdown.)1
Other offshore wind developments provide context for Revolution Wind’s entry into service. (The reporting also covers projects in the United States and the North Sea.)23 Sunrise Wind’s foundations are complete, and its 924-MW project is expected to reach full operation in the second half of next year. (Canary Media reports the construction status, capacity, and expected timing.)3 Borkum Riffgrund 3, a 913-MW project in the North Sea, has begun commercial operation and is included in Ørsted’s 8.1-GW offshore construction portfolio. (POWER Magazine reports these project details.)2 Those two projects are described at different stages: Sunrise Wind has completed foundations, while Borkum Riffgrund 3 has started commercial operation. (The sources state these distinct milestones.)23 The reported capacities for Sunrise Wind and Borkum Riffgrund 3 are project-specific figures, while the 8.1-GW figure covers the broader portfolio. (The source associates the portfolio total with Ørsted’s construction work.)23
BloombergNEF revised its forecast for U.S. offshore wind construction by 2035, reducing the projected total from 39 GW to 5.9 GW. (Canary Media reports both forecast figures.)3 The revision is a change in a forecast, not a report that the already-built Revolution Wind project has been removed from service. (The source describes a future build-out estimate.)13 A supported account says Revolution Wind’s start helps counterbalance the smaller pipeline implied by BloombergNEF’s revised outlook. (This interpretation is marked supported.)1 The project’s 65 turbines and the national forecast use different measures: one counts installed equipment at a named project, and the other estimates future U.S. capacity. (The cited facts identify those scopes.)13 Taken together, the reports describe one project entering commercial operation while the broader forecast for offshore wind construction has been cut. (The first is an operating milestone; the second is a revised projection.)13
Disagreements
Where the sources do not matchHistory
How it came to this- August 2025First stop-work orderThe Trump administration ordered work to stop, citing national security concerns.
- December 2025Further suspension orderA second order was issued as part of an effort to halt several offshore wind projects.
- Date not specifiedPreliminary injunctionA federal judge allowed work on the project to proceed.
- September 2026Final turbine installedThe project’s last turbine was installed.
- October 2026Commercial operations beginRevolution Wind reached commercial operation.
- NowOctober 2026 Revolution Wind entered commercial operation
Impact
Spreading outward, level by level- Level 1Project operations
The project is reported as fully operational and expected to deliver clean electricity to the New England grid.1
Fact - Level 2Utility purchasers
Power purchase agreements are in place with utilities in Rhode Island and Connecticut, including Eversource and United Illuminating.2
Fact - Level 3Offshore wind development outlook
The project’s entry into service may partly counterbalance the reduced U.S. offshore wind build-out outlook; the supported account describes it as helping offset the reduced pipeline forecast.