Belgium orders Google to stop work at nearly finished Wallonia data centre
The order concerns a facility whose structural work was complete, although the amended planning permission had been revoked. The dispute centres on a redesign that combined two planned centres and proposed drawing cooling water from a nearby river.
Stokis said 300 workers were verbally told to stop work, with written confirmation sent to Google.1
The building at the centre of the alleged illegal-construction report covers about 3 hectares.12
Google's proposed liquid-cooling system would draw 600 m³ of water per hour from the Sambre River.1
Story
The Wallonia construction order and the permit dispute behind itBelgian authorities have directed Google to stop building a data centre in Wallonia because changes the company sought to make to its original planning terms were not authorised.1 The order came after inspectors found that the structure was nearly complete and its framework had already been finished, despite refusal of the relevant permit.1 The scale described in the reporting is specific: the building covers about 3 hectares, while the wider business park occupies 50 hectares.1 Stokis said 300 workers received a spoken instruction to halt their work, and that Google was subsequently sent written confirmation.1
The location is a former coal-mining site at Aiseau-Presles, roughly 15 km west of Charleroi, within a business park measuring 50 hectares.1 The facility under construction takes up about 3 hectares of that park, or 7.4 acres, and is one of three centres Google had originally intended to build there.1 The 50-hectare figure describes the whole park, not the building named in the alleged offence; that building is described as covering 3 hectares.1 A separate account of the stop-work order likewise identifies the former mining property as an area of some 50 hectares, reinforcing the distinction between the site and the structure.12
Google's permit from 2024 allowed three smaller data centres using air cooling, setting out a different arrangement from the one later proposed.1 In 2025, the company applied to combine two of those planned centres into one larger facility and replace air cooling with a liquid-cooling system.1 The proposed system would have drawn 600 m³ of water per hour from the nearby Sambre River.1 That change in design matters to the sequence of approvals: the initial permission covered three smaller air-cooled buildings, while the later application described a merged facility and a different source of cooling.1
Local authorities first approved the 2025 amendments, but residents and protest groups challenged that decision.1 In August, Wallonia's infrastructure minister, François Desquesnes, revoked the modified permit after those appeals, citing concerns about drought.1 The initial approval in April and the later revocation describe successive stages in the same permitting dispute, rather than separate projects.1 The authorities' current stop-work action follows the lack of approval for Google's requested changes, while the construction had advanced to the point that inspectors saw completed structural work.1
The regional administration is also referring the matter to public prosecutors, according to Nicolas Yernaux, a spokesperson for the regional government.1 Yernaux characterized the alleged breach as major and described it as construction without legality involving a building of 3 hectares.1 A second report attributes similar wording to Yernaux and gives the building's area as three hectares, with an equivalent of 7 acres.2 These accounts concern an allegation being put before prosecutors; they do not report a final court finding about the construction.12
Greenpeace released a report containing footage from a drone, which it said showed construction continuing even though the required permits were not in place.1 That report provides an account of activity at the site, while inspectors separately recorded that the building was almost finished and its structural phase complete.1 Stokis's account adds the practical reach of the order: 300 workers were told verbally to stop, and Google received written confirmation.1 Together, the reporting describes a project that had progressed substantially, a permit dispute over changes to its design, and an instruction applying to work at the site.1
Google said it was committed to keeping dialogue with regional authorities open and collaborative.1 The company has also appealed the permit decision to Belgium's council of state, where a ruling is expected on 7 January.1 That appeal means the dispute over the modified permission is still before a national body, even as the regional stop-work order and referral to prosecutors form part of the current response.1 The reported date for the expected ruling identifies a pending step; the available account does not state what the council will decide.1
The Wallonia case is one of the latest legal disputes facing Google in Europe as large technology companies seek to expand data-centre capacity in support of the AI boom.1 The Finnish case cited in the reporting concerns a planned Google data centre in the country's rural north, rather than the Wallonia facility.1 In October, Finland opened a criminal investigation into possible environmental-law breaches there and stopped work until environmental impact assessments are completed.1 The comparison shows another European dispute involving a Google data-centre project and environmental review, but the Finnish account describes a criminal investigation and assessment process, not the Belgian permit history.1
The central contrast in Wallonia is between the original permission for three smaller, air-cooled centres and the later proposal to merge two and use water-based cooling.1 The proposed hourly draw of 600 m³ from the Sambre and the minister's stated drought concerns link the redesign to the reason given for revoking its permit.1 The affected areas and people are counted in different ways: the building is about 3 hectares, the business park is 50 hectares, and Stokis identified 300 workers who received the order.1 The facts establish the order, the status of construction, the permit sequence and the pending appeal, while leaving the council's eventual ruling unresolved.1
Structure
Who is connected to whom- 1Google
- part of →Fact
- invests in →Fact
- supplies →Fact
- uses →Fact
- ← partners withFact
Disagreements
Where the sources do not matchHistory
How it came to this- 2024Original permit covered three smaller air-cooled centresGoogle's permit allowed construction of three smaller data centres using air cooling.
- 2025Google applied to change the designThe application proposed merging two centres into one larger facility and switching to liquid cooling, drawing water from the Sambre River.
- AprilAmendments initially approvedThe regional administration initially approved the proposed changes.
- AugustModified permit revokedAfter appeals by residents and protest groups, the infrastructure minister revoked the modified permit over drought concerns.
- Not statedAuthorities ordered work to stopAuthorities ordered Google to halt construction because the requested changes to the original planning terms lacked approval.
- Now300 Workers told to stop work at the Wallonia data-centre site
- 7 JanuaryA ruling is expected in Google's appeal to Belgium's council of state; the reported account does not state the outcome.
Impact
Spreading outward, level by level- Level 1Workforce at the site
Stokis said 300 workers received a verbal instruction to stop work, later confirmed in writing to Google.1
Fact - Level 2Construction project
Inspectors found the building almost finished, with structural work completed, despite the permit having been refused.1
Fact - Level 3Prosecutorial referral
The regional government spokesperson said a report alleging illegal construction of a 3-hectare building was being submitted to public prosecutors; this is an allegation, not a reported final court finding.1
Fact - Level 4Permit dispute
Google appealed the permit decision to Belgium's council of state, leaving the dispute over the modified permission unresolved pending a ruling.1
Fact
Ahead
Checked automatically when due; the result goes to the track recordA ruling is expected in Google's appeal to Belgium's council of state; the reported account does not state the outcome.